Skip to main content

Waterloo Station update

03.02.2021

Waterloo Piling Works Waterloo Piling Works
Waterloo Station site Waterloo Station site
Waterloo Waterproofing Waterloo Waterproofing
Waterloo Waterproofing Waterloo Waterproofing

Construction is progressing to build Waterloo Station after completion of excavation and concrete lining by the tunnelling contractor.

Piling was completed in late 2020, followed by waterproofing, installation of steel reinforcement and concrete pouring work to form the floor. These activities are due to be completed soon.

More than 75,000 tonnes of concrete and about 8,000 tonnes of steel will be used to build the station box.

About 16,000 square metres of waterproofing is being used to line the station area, enough to almost line the surface of the Sydney Cricket Ground. 

Southwest metro upgrade - update

First look inside Chatswood Dive

Back to top