Major milestone as Metro Northwest completes its first full test

15.01.2019

An arial shot looking down on the station platform as a Sydney Metro Train arrives at the platform next to a Sydney Trains train at Chatswood Station. An arial shot looking down on the station platform as a Sydney Metro Train arrives at the platform next to a Sydney Trains train at Chatswood Station.
An on the ground view looking across the station platform as a Sydney Metro Train arrives at the platform next to a Sydney Trains train at Chatswood Station. An on the ground view looking across the station platform as a Sydney Metro Train arrives at the platform next to a Sydney Trains train at Chatswood Station.

Australia’s first driverless metro train has completed its first journey along the entire length of Sydney’s new $8.3 billion Metro Northwest railway line.

 

The train arrived at Chatswood Station’s Metro platforms on January 14, having travelled 36km from the new Tallawong Station in Sydney’s northwest as part of the intensive testing process.

Over the past three months, major upgrade work inside the existing railway tunnels between Epping and Chatswood has been underway to allow this major Metro milestone to occur.

Platform screen doors have now been installed at all Sydney Metro platforms, including between Epping and Chatswood.

These platform screen doors are a major customer safety feature of all Sydney Metro stations.

They keep people and objects like prams away from the tracks, creating a physical barrier at the edge of the platform which also allows trains to get in and out of stations much faster.

The platform doors only open and close at the same time as the train doors and are a key safety and technology feature of Sydney Metro.

The testing of the new trains and systems is well underway at the new stations and now starting between Epping and Chatswood.

About 19,000km of train testing has taken place so far on the Sydney Metro system, with 17 of the fleet of 22 trains delivered.

Onboard train systems will be tested over the coming months as well as signalling, braking and acceleration at different speeds in the tunnel.

Metro rail is currently being extended from Chatswood to Bankstown, with services expected to start in 2024 – when Sydney will have 31 metro stations and a 66km standalone metro railway with trains running every four minutes in the peak in each direction.