Skip to main content

Entire skytrain deck locked into place

13.06.2017

An on the ground view looking up at the construction of the final span of Sydney Metro's skytrain bridge  at night.
An on the ground view looking up at two construction workers on a crane lift as the final segment is nearing completion.
An on the ground view looking up at the construction work of the final span being lifted into place by a gantry crane at Sydney Metro's  Rouse Hill Drive site.

The entire deck of Sydney Metro’s 4km elevated skytrain is now locked in place high in the air between Bella Vista and Rouse Hill, with the last massive concrete segment lifted and fixed into position.

 

The skytrain sits an average 9m in the air alongside Windsor Road and Old Windsor Road, with new metro trains to run on it every four minutes in the peak.

As part of the skytrain construction process:

  • 1,128 massive concrete segments were lifted an average 9m into the air to form the skytrain deck;
  • Each segment weighed between 56 tonnes and 147 tonnes;
  • 80,000 tonnes of concrete was used for the skytrain deck – that’s the equivalent of 81 Olympic swimming pools of concrete;
  • The segments were tensioned tight internally with about 1,400km of steel cables.

Two huge white 600 tonne horizontal cranes did the heavy lifting, and they will now be dismantled.

The skytrain deck sits on 120 concrete piers.

More than 4,600 people have worked on the skytrain.

Work continues on the new 270m long railway bridge over Windsor Road at Rouse Hill at the end of the skytrain, which will take new metro services to the new Cudgegong Road station.

The bridge’s two towers are in place, 45m above Windsor Road, and 32 steel cables will soon be installed to support the bridge deck.

Revitalisation of Central Station underway

New entrance to improve connectivity at Victoria Cross

Back to top